PRESERVATION AND PROTECTION OVERALL MAXIMUM COST SCHEDULE

 

**Additional Amounts for Wet/Radiant Winterizations:  If a property is located in a state where winterization is required, and the property has hot water heat, add $250 per unit.
 

Philadelphia HOC

1  Unit

2  Units

3  Units

4  Units

Michigan

$1,250

$1,500

$1,750

$2,000

Variations from General Requirements

 


 

LOCK CHANGE / SECURING SERVICE COST SCHEDULE

 

Maximum Allowable Securing Fee

In-Ground Pools

Above-Ground

Pools

Hot-Tub, Jacuzzi, Spa

Temporary
Roof Repairs

$200

$1.65/sq.ft., $750 max.

$100

$50

$250

Variations from General Requirements

 


 

BOARDING SERVICE COST SCHEDULE

 

Boarding

½” plywood

Boarding

5/8” plywood

Boarding

¾” plywood

Screening

$.55 / UI

$.65 / UI

$.75 / UI

$.45 / UI

Variations from General Requirements

Note:

Key:  UI = United Inch

Definition - United Inch equals length plus width.

 


 

DEBRIS REMOVAL SERVICE COST SCHEDULE 

 

Per Cubic Yard

Maximum Allowable

for 1 Unit

Maximum Allowable

for 2 Units

Maximum Allowable

for 3 Units

Maximum Allowable

for 4 Units

Vehicle Removal

$30

$360

$450

$540

$630

$  50

Variations from General Requirements

 

 

 

YARD MAINTENANCE SERVICE REQUIREMENTS AND COST SCHEDULE

 

Initial Cut

Up to

5,000 s.f.

Initial Cut

5,001 to 10,000 s.f.

Initial Cut

10,001 to

15,000 s.f.

Recut

Up to

5,000 s.f.

Recut

5,001 to 10,000 sf.

Recut

10,001 to

15,000 s.f.

Trim Shrubs

Snow Removal

$45

$65

$85

$30

$40

$50

$35

$45

Variations from General Requirements

 


 

WINTERIZATION SERVICE COST SCHEDULE

 

Dry Heat:

1 Unit

Dry Heat:

Additional Units

Wet Heat: Steam Heat

1 Unit

Wet Heat:

Additional

Units

Radiant Heat: Hot Water Heat

1 Unit

Radiant Heat:

Additional Units

$75

$25 / Unit

$120

$55 / Unit

$450

$90 / Unit

 Variations from General Requirements

 

Note:  The cost of anti-freeze is included in the cost allowable.

 

97-31 Prices

$50

$50 / Unit

$60

$60 / Unit

N/A

N/A


 

PHOTOS

 

$1.00

 


 

Variations from General Requirements

 

PRESERVATION AND PROTECTION

 

NO VARIATION TO THE GENERAL REQUIREMENTS.

 
  Preservation and Protection Cost Schedule
 
 

 

SECURING

 

Use padlock and hasps only (Master lock key code A389).  Remove existing knob locks on prime entry doors.  If no door exists, use plywood door with padlock and hasp.  Bracing is allowed only with prior written approval in accordance with the diagrams on pages 16 and 17 of attachment 3.

 

 

Securing Cost Schedule

 
 

 

BOARDING

 

In all areas, remove but do not replace broken glass; bolt board openings where glass is broken with prior approval.

 

There is no required thickness of plywood per the guidelines. Ensure that the thickness of plywood being used is documented on the update/bid and that the corresponding allowable amount is used for bidding/invoicing purposes.

 

Boarding Cost Schedule  
 

 

DEBRIS REMOVAL

 
Remove doors from refrigerators / freezers left in property.  $15 per appliance to remove doors.
 
Debris Removal Cost Schedule
 
 

 

YARD MAINTENANCE

 

NO VARIATION FROM GENERAL REQUIREMENTS.

 

  Yard Maintenance Cost Schedule
 
 

 

WINTERIZATION

 

Winterize year round regardless of the month the property is secured.  Install new submersible sump pump if existing pump is inoperable or missing from the property.

 

Type of Service: 

Allowable Cost:

Sump Pump

$15

Sump Pump replacement

$225

Water meter removal

$25

Pumping water from basement

$100

Posting signs / stickers for winterization

$10

 

Winterization Cost Schedule