PRESERVATION AND PROTECTION OVERALL MAXIMUM COST SCHEDULE
Santa Ana HOC |
1 Unit |
2 Units |
3 Units |
4 Units |
Pacific/Hawaii |
$1,000 |
$1,050 |
$1,100 |
$1,150 |
Variations from General Requirements
LOCK CHANGE / SECURING SERVICE COST SCHEDULE
Maximum Allowable Securing Fee |
In-Ground Pools |
Above-Ground Pools |
Hot-Tub,
|
Temporary |
$200 |
$1.65/sq.ft., $750 max. |
$100 |
$50 |
$250 |
Variations from General Requirements
BOARDING SERVICE COST SCHEDULE
Boarding ½” plywood |
Boarding 5/8” plywood |
Boarding ¾” plywood |
Screening |
$.60 / UI |
$.70 / UI |
$.80 / UI |
$.50 / UI |
Variations from General Requirements
Note:
Key: UI = United Inch
Definition - United Inch equals length plus width.
DEBRIS REMOVAL SERVICE COST SCHEDULE
Per Cubic Yard |
Maximum Allowable for 1 Unit |
Maximum Allowable for 2 Units |
Maximum Allowable for 3 Units |
Maximum Allowable for 4 Units |
Vehicle Removal |
$30 |
$360 |
$450 |
$540 |
$630 |
$100 |
Variations from General Requirements
YARD MAINTENANCE SERVICE REQUIREMENTS AND COST SCHEDULE
Initial Cut Up to 5,000 s.f. |
Initial Cut 5,001 to 10,000 s.f. |
Initial Cut 10,001 to 15,000 s.f. |
Recut Up to 5,000 s.f. |
Recut 5,001 to 10,000 s.f. |
Recut 10,001 to 15,000 s.f. |
Trim Shrubs |
Snow Removal |
$70 |
$90 |
$110 |
$40 |
$50 |
$60 |
$45 |
N/A |
Variations from General Requirements
WINTERIZATION SERVICE COST SCHEDULE
Dry Heat: 1 Unit |
Dry Heat: Additional Units |
Wet Heat: Steam Heat 1 Unit |
Wet Heat: Additional Units |
Radiant Heat: Hot Water Heat 1 Unit |
Radiant Heat: Additional Units |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
Variations from General Requirements
Note: The cost of anti-freeze is included in the cost allowable.
97-31 Prices |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
$1.50
NO VARIATION TO THE GENERAL REQUIREMENTS.
Replace front and rear door lock with new Kwikset or equivalent lock. If other exterior doors cannot be secured with existing hardware, install a 4-inch heavy-duty barrel bolt. Garages and outbuildings are to be secured by installing a hasp lock and securing it with a key operated padlock. Turn off all utilities. Contact utility companies to terminate service.
Swimming Pools:
Pools must be secured within 24 hours of discovery of the pool. Comply with local laws and ordinances. The costs for permits to drain pools/spas by local governments are included in the maximum limit and will be reimbursed based on the actual cost incurred.
Prior approval is not required to drain / secure swimming pools.
Type of Service |
Allowable Cost |
Pool Draining |
$125 |
Pool and Spa Draining |
$150 |
Spa Only |
$50 |
Lock Gates to Pool w/Padlock and Hasp |
$20 |
See pages 26 and 27 of this attachment for specific boarding instructions and diagram. Where there is no primary door, install security door with padlock. These pages indicate that all openings are to be boarded with 5/8” plywood except for security doors. Security doors require ¾” plywood.
Boarding Cost Schedule
Mortgagees are not to perform any interior debris removal without specific M&M contractor approval. (This includes Interior H/Hazard removal per the email from Tracy Hager (MID) on 1/23/04.)
Debris Removal Cost Schedule
Grass should be cut year round. One cut a month should be sufficient, however, two cuttings a month may be required after a rainy period. A photograph of the front and rear yards is required “before” and “after” the initial lawn cut and final lawn cut.
Mortgagees will not be reimbursed for properties with desert landscaping except for weed removal. Weed removal will be reimbursed as a recut.
Since dry grass and weeds could be considered a fire hazard, mortgagees are to maintain the lawns in accordance with local code.
Yard Maintenance Cost Schedule
DO NOT WINTERIZE.